Four phases in three weeks. Features are agreed first, the whole site is built and working before anyone polishes it, and the refinement work happens on the real thing rather than on mockups. This page is the single source of truth — status, owners, deadlines and decisions all live here.
Deliberately sequential where it matters: nothing gets designed or written until the thing it describes actually exists and works.
Phase 3 runs two streams at once — content and visuals refine the pages while the build side hardens the accounts, database and security underneath.
Everything else can move. These cannot — each one releases the next phase, so a day lost here is a day lost at the end.
Twenty-two days from kick-off to go-live. Amber days are handovers between people — each one has to land on time for the next phase to start.
Three weeks with one developer buys a complete, polished public site with real accounts. Everything requiring cross-team data or a rewards engine ships after launch, once the site is earning its keep.
Owner tags: ALAN manager · JM content · LEO · RUBY visual design · BUILD Louis
The biggest time cost on a project this size is feedback arriving in five places at once. From this week there is exactly one place to look and one place to comment.
Five people, four clear lanes. The important division: features and page structure come from the build side; Leo and Ruby make it look right; JM makes it read right. Each deliverable has exactly one owner — shared ownership is how deadlines slip.
| Who | Owns | Must deliver by |
|---|---|---|
| Alan · Manager | Feature decisions, domain and IT requests, compliance sign-off, final approval. Unblocks anything that needs another department. | Domain request 23 Jul · Features 27 Jul · Sign-off 12 Aug |
| JM · Content | All written copy in both languages, including course descriptions, buttons and the emails members receive. | Final copy 10 Aug |
| Leo & Ruby · Design | Visual quality and brand consistency across the built site — colour, type, spacing, imagery, icons and illustrations, delivered as a Figma refinement pack plus exported assets. They do not define features or page structure. | Visual pack 10 Aug |
| Louis · Build | The entire build and everything behind it — pages, features, accounts, member database, security configuration, hosting, testing and launch. Owns the backend outright. | All features working 5 Aug · Live 13 Aug |
| Platform team | Deployment support only. Publishes the site to its final address and keeps that pipeline working — no development, no database access, no responsibility for Academy data. | Before 13 Aug |
Named early so they can be managed, rather than discovered in the final week.
The prototype is further along than a typical three-week start — the design system, both languages and the full user experience already exist and are demonstrable.
| Area | Status | Remaining before launch |
|---|---|---|
| Public pages | Built | Apply final visuals and approved copy |
| Both languages | Built | Translate the new and revised copy |
| Design system | Built | Apply Leo & Ruby's brand refinements |
| Mobile & accessibility | Built | Re-test after the visual update |
| Membership levels | Awaiting answers | Confirm the rules, then build them |
| Member accounts | In build | Replace the demo login with real accounts |
| Course & lesson pages | Not started | Build from the confirmed course list |
| Hosting & domain | Waiting on IT | Temporary address live; real domain requested |
| Points & referrals | September | Counted from launch, displayed later |
| Partner dashboard | Demo only | Real data in September |
This plan assumes the feature answers land on 27 July and that no additional pages are added afterwards. If a date slips, the launch date holds and scope moves to September — that trade is the manager's to make, and should be made in the week it happens rather than in the final week.